Process data that is generated when a long-lived process
is invoked can become too large, resulting in lower LiveCycle performance
and the use of unnecessary disk space. It is good practice to purge
process data when records are no longer necessary.
You can use Administration Console to perform a one-time purge
of obsolete records, or to schedule regular automatic purges. Other
methods for purging obsolete records are discussed in Purging process data.
Access the Job Purge Scheduler pageIn Administration
Console, click Health Monitor in the upper-right corner of the page.
Click the Job Purge Scheduler tab.
Information
about any currently scheduled purges is displayed in the Job Purge Scheduler
Information box.
Note: Clicking Stop Scheduler
stops any purges scheduled in the future, but does not stop a purge
job that is already underway.
Schedule a one-time purgeSelect One Time Only.
In the Purge Completed Records Filter area, specify the number
of days or weeks after which a record is deemed obsolete and ready
for purging.
Note: Records related to processes
that have not been completed are not purged, even if they are older
than the specified age.
Specify when the purge will occur. Select the Use Current
Date & Time checkbox, or clear the checkbox and click the calendar
and clock icons to specify the date and time when the purge will
be performed.
Note: If you specify a start date
and time that is in the past, the purge occurs immediately when
you click Start Scheduler.
Click Start Scheduler. Any previously scheduled scheduler
settings are replaced with the new settings.
Configure an automatic purge scheduleSelect Recur Every
and specify the number of days or weeks between purges.
In the Purge Completed Records Filter area, specify the number
of days or weeks after which a record is deemed obsolete and ready
for purging. You cannot set the value to 0.
Note: Records related to processes that have not been
completed are not purged, even if they are older than the specified
age.
Specify when the purges will begin. Select the Use Current
Date & Time checkbox, or clear the checkbox and click the calendar
and clock icons to specify the date and time when the purge will
be performed.
Note: If you specify a start date and time that
is in the past, LiveCycle calculates the logical next start date
based on the date you specified. For example, if you schedule the
job purges to occur weekly beginning April 7, and it is now April
9, the first purge occurs April 14.
Click Start Scheduler. Any previously scheduled scheduler
settings are replaced with the new settings.
|
|
|