Before you begin the upgrade process, you must perform
several tasks to prepare your environment for upgrading:
Run the Enterprise Readiness Tool (ERT) on your current
LiveCycle ES Update 1 or LiveCycle ES2 installation. See Using the Enterprise Readiness Tool for
more information.
Read the Upgrade Checklist and Planning guide
and complete all the verification tasks and validation checks on
your existing LiveCycle ES Update 1 or LiveCycle ES2 environment.
Based on the findings of the Upgrade Checklist/ERT, update
any QPAC-based workflows to DSC-based workflows either using the
Workbench (versions 8.2.1, 9.0, or 9.5 as applicable) Process Upgrade
Tool OR manually writing DSC/Service operations for the same.
Refer to the platform matrix, and prepare the software infrastructure
required for the upgrade. Complete any manual steps before upgrading
your LiveCycle instance. For example, if a new application server
is required, refer to the relevant sections of 'Preparing to Install
LiveCycle ES3' guide to prepare the new application server instance.
Apply the latest patches to your application server, as required
in the LiveCycle ES3 Supported Platform Combinations document.
Or, if a new version of Database server is required then, data from older
Database server instance must be migrated to the newer Database server
instance.
Back up the existing LiveCycle environment.
|
|
|